Project status

2030

Riga Ropax Terminal launch

2028 - 2029

Active construction phase

Construction of Terminal, necessary utilities and communications, public spaces, mobility network

2024 - 2026

Active preparation phase, attraction of terminal financing

Project details, partnerships, public infrastructure decision, coordination phase

2023-2024

Approval of the local plan by Riga City Council and Architectural competition

2022

Project planning

Establishment of the Freeport Work Group

 

2021

Eksportosta management plan

Feasibility study, terminal design

2020

Local plan approval

Conclusion of MOU between the private partner and the Freeport of Riga Authority

2019

Sketch design

Local plan development phase

2018

Riga City Council rules on use of Eksportosta territory

Riga City Council adopts a decision on the development of a local plan for the southern part of the EO